Audits
Program Manuals
Topical Reports
FSAR Chapters
ACRS Reviews
Correspondence
Meetings
Inspections
Activities
| Name | Type | Start | End | Duration (days) | RAI Req | RAI Resp | Accessions |
|---|---|---|---|---|---|---|---|
| Containment Systems Audit | Audit | 2017-03-29 | 2019-11-26 | 972 | 0 | 0 | 5 |
| PRA Audit | Audit | 2017-03-31 | 2018-03-05 | 339 | 0 | 0 | 4 |
| Safety Classification of Passive Nuclear Power Plant Electrical Systems, | Program Manual | 2017-04-03 | 2017-04-03 | 0 | 0 | 0 | 1 |
| Topical Report TR-0915-17772 | Topical Report | 2017-04-06 | 2018-11-19 | 592 | 0 | 1 | 3 |
| FSAR Chapter 4: Reactor | Fsar Chapter | 2017-04-10 | 2020-07-23 | 1200 | 0 | 0 | 5 |
| FSAR Chapter 3: Design of Structures, Components | Fsar Chapter | 2017-04-10 | 2020-07-23 | 1200 | 2 | 0 | 5 |
| Regulatory Audits 2017 | Audit | 2017-04-25 | 2017-12-27 | 246 | 0 | 0 | 5 |
| FSAR Chapter 5: Reactor Coolant System | Fsar Chapter | 2017-04-26 | 2020-07-23 | 1184 | 0 | 1 | 5 |
| FSAR Chapter 9: Auxiliary Systems | Fsar Chapter | 2017-04-26 | 2020-07-23 | 1184 | 0 | 0 | 5 |
| Loss-Of-Coolant Accident Evaluation Model, | Topical Report | 2017-04-27 | 2020-06-22 | 1152 | 0 | 5 | 5 |
| FSAR Chapter 7: Instrumentation and Controls | Fsar Chapter | 2017-05-06 | 2020-07-22 | 1173 | 1 | 0 | 5 |
| NuScale Advanced Sensors, | Program Manual | 2017-05-16 | 2017-05-18 | 2 | 0 | 0 | 2 |
| I&C Technical Specifications. | Program Manual | 2017-05-17 | 2017-05-17 | 0 | 0 | 0 | 1 |
| - TR-1015-18653, Design of Highly Integrated Protection System Platform, Revis | Topical Report | 2017-05-23 | 2017-05-31 | 8 | 0 | 0 | 2 |
| NuScale Power Critical Heat Flux Correlation NSP2, | Topical Report | 2017-05-30 | 2019-01-03 | 583 | 0 | 0 | 3 |
| Loss Of Coolant Accident Evaluation Model. | Topical Report | 2017-05-30 | 2020-06-22 | 1119 | 0 | 0 | 5 |
| Evaluation Methodology For Stability Analysis Of the NuScale Power Module. | Topical Report | 2017-06-07 | 2019-12-19 | 925 | 0 | 3 | 5 |
| FSAR Chapter 15: Transient and Accident Analysis | Fsar Chapter | 2017-06-12 | 2020-07-23 | 1137 | 0 | 0 | 5 |
| FSAR Chapter 20: Generic Issues | Fsar Chapter | 2017-06-21 | 2020-08-28 | 1164 | 1 | 0 | 5 |
| Summary Of The May 23, 2017, Category 1, Public Teleconference To Discuss The D | Topical Report | 2017-06-26 | 2018-10-25 | 486 | 0 | 0 | 3 |
| NuScale Instrument Setpoint Methodology Technical Report | Topical Report | 2017-06-29 | 2020-05-20 | 1056 | 0 | 0 | 4 |
| FSAR Chapter 18: Human Factors Engineering | Fsar Chapter | 2017-07-25 | 2020-08-28 | 1130 | 0 | 0 | 5 |
| Presentation to the ACRS Subcommittee, NuScale TR-0116-20825 Rev. 1, Applicabil | Topical Report | 2017-09-20 | 2018-03-07 | 168 | 0 | 0 | 2 |
| ACRS Review 2017-09 | Acrs Review | 2017-09-20 | 2017-09-20 | 0 | 0 | 0 | 1 |
| FSAR Chapter 8: Electric Power | Fsar Chapter | 2017-09-26 | 2020-08-28 | 1067 | 0 | 0 | 5 |
| Accident Source Term Methodology | Topical Report | 2017-10-05 | 2019-10-18 | 743 | 0 | 0 | 5 |
| Request for Public Meeting to Address Proposed Limitation and Condition 4.5 in t | Topical Report | 2017-10-12 | 2017-11-14 | 33 | 0 | 0 | 2 |
| NuScale DCA Review Focus Areas | Program Manual | 2017-11-13 | 2017-12-12 | 29 | 0 | 0 | 2 |
| NuScale Generic Technical Guidelines, | Topical Report | 2017-11-30 | 2019-05-31 | 547 | 0 | 0 | 3 |
| "Containment Vessel Ultimate Pressure Integrity, TR-0917-56119 (NRC Docket No. 5 | Topical Report | 2017-12-14 | 2019-06-07 | 540 | 0 | 0 | 2 |
| Regulatory Audits 2018 | Audit | 2018-01-05 | 2018-12-28 | 357 | 1 | 2 | 5 |
| Shutdown Capability of the Nu Scale Power Module, | Program Manual | 2018-01-17 | 2018-01-17 | 0 | 0 | 0 | 1 |
| NuScale Source Term Revision, | Program Manual | 2018-01-17 | 2018-01-23 | 6 | 0 | 0 | 2 |
| NuScale Comprehensive Vibration Assessment Program, | Topical Report | 2018-01-20 | 2019-07-31 | 557 | 0 | 0 | 2 |
| Shutdown Capability of the NuScale Power Module, | Program Manual | 2018-02-01 | 2018-02-08 | 7 | 0 | 0 | 2 |
| FSAR Chapter 19: PRA and Severe Accidents | Fsar Chapter | 2018-02-10 | 2020-07-23 | 894 | 0 | 0 | 5 |
| FSAR Chapter 10: Steam and Power Conversion | Fsar Chapter | 2018-03-15 | 2020-08-28 | 897 | 0 | 0 | 5 |
| FSAR Chapter 14: Initial Test Program | Fsar Chapter | 2018-03-15 | 2020-08-28 | 897 | 0 | 0 | 5 |
| FSAR Chapter 17: Quality Assurance | Fsar Chapter | 2018-03-15 | 2020-08-28 | 897 | 0 | 1 | 5 |
| FSAR Chapter 16: Technical Specifications | Fsar Chapter | 2018-03-15 | 2020-07-23 | 861 | 0 | 0 | 5 |
| FSAR Chapter 6: Engineered Safety Features | Fsar Chapter | 2018-03-15 | 2020-07-23 | 861 | 0 | 0 | 5 |
| FSAR Chapter 21: Multi-Module Design | Fsar Chapter | 2018-03-15 | 2020-08-28 | 897 | 0 | 0 | 5 |
| FSAR Chapter 12: Radiation Protection | Fsar Chapter | 2018-03-15 | 2020-08-28 | 897 | 0 | 0 | 5 |
| FSAR Chapter 1: Introduction and General Description | Fsar Chapter | 2018-03-15 | 2020-07-22 | 860 | 0 | 0 | 5 |
| FSAR Chapter 2: Site Characteristics | Fsar Chapter | 2018-03-15 | 2020-08-28 | 897 | 0 | 2 | 5 |
| FSAR Chapter 11: Radioactive Waste Management | Fsar Chapter | 2018-03-15 | 2020-08-28 | 897 | 0 | 0 | 5 |
| FSAR Chapter 13: Conduct of Operations | Fsar Chapter | 2018-03-15 | 2020-08-28 | 897 | 0 | 0 | 5 |
| NuScale Power Comprehensive Vibration Assessment Program - Audit Report Summary | Program Manual | 2018-04-24 | 2018-04-24 | 0 | 0 | 0 | 1 |
| NuScale Power Containment Leak Rate Test Program, | Program Manual | 2018-05-15 | 2018-05-31 | 16 | 0 | 0 | 2 |
| Safety Evaluation of NuScale TR-0118-58005, Improvements in SSFI Analysis, Rev 2 | Topical Report | 2018-05-16 | 2020-10-05 | 873 | 0 | 0 | 2 |
| ACRS Review 2018-06 | Acrs Review | 2018-06-01 | 2018-06-29 | 28 | 0 | 0 | 2 |
| ACRS Response Letter (Oedo-18-00321) - Safety Evaluation Nuscale TR-0616-48793, | Topical Report | 2018-06-29 | 2018-06-29 | 0 | 0 | 0 | 3 |
| Risk-Informed Review of NuScale Initial Test Program | Program Manual | 2018-07-27 | 2018-08-01 | 5 | 0 | 0 | 2 |
| NuScale Accident Source Terms Methodology Options | Program Manual | 2018-08-08 | 2018-08-08 | 0 | 0 | 0 | 2 |
| Line Breaks in NuScale Plant Results, Status, and Plans for Closure, | Program Manual | 2018-08-13 | 2018-08-13 | 0 | 0 | 0 | 1 |
| ACRS Presentation: NuScale Instrumentation and Controls Design Overview, | Program Manual | 2018-08-21 | 2018-08-23 | 2 | 0 | 0 | 2 |
| ACRS Review 2018-08 | Acrs Review | 2018-08-21 | 2018-08-23 | 2 | 0 | 0 | 2 |
| NuScale Power Module Seismic Analysis, | Topical Report | 2018-09-28 | 2019-04-03 | 187 | 0 | 0 | 2 |
| Nuclear Steam Supply System Advanced Sensors Technical Report, | Topical Report | 2018-10-01 | 2020-05-20 | 597 | 0 | 0 | 3 |
| Pipe Rupture Hazards Analysis. | Topical Report | 2018-10-03 | 2019-07-31 | 301 | 0 | 0 | 5 |
| Subchannel Analysis Methodology. | Topical Report | 2018-10-15 | 2018-12-04 | 50 | 0 | 0 | 5 |
| CNV Peak Containment Pressure Closure Meeting - Part 2 Incoming RAI Discussion, | Program Manual | 2018-10-15 | 2018-10-15 | 0 | 0 | 0 | 1 |
| ACRS Review 2018-10 | Acrs Review | 2018-10-15 | 2018-10-30 | 15 | 0 | 0 | 2 |
| NuScale PRA Overview, | Program Manual | 2018-10-30 | 2018-10-30 | 0 | 0 | 0 | 1 |
| Technical Specifications Regulatory Conformance and Development, | Topical Report | 2018-10-31 | 2020-05-20 | 567 | 0 | 0 | 4 |
| Fuel Storage Rack Analysis, | Topical Report | 2018-11-05 | 2018-11-05 | 0 | 0 | 0 | 1 |
| Effluent Release (GALE Replacement) Methodology and Results, | Topical Report | 2018-11-13 | 2018-11-13 | 0 | 0 | 0 | 1 |
| LTC RAI Closure Plan, | Program Manual | 2018-11-14 | 2018-11-29 | 15 | 0 | 0 | 2 |
| Scaling RAI Closure Meeting, | Program Manual | 2018-12-04 | 2018-12-04 | 0 | 0 | 0 | 1 |
| NuScale Comprehensive Vibration Assessment Program Measurement and Inspection Pl | Topical Report | 2018-12-07 | 2019-10-03 | 300 | 0 | 0 | 3 |
| ACRS Presentation Chapter 2 - Site Characteristics and Site Parameters, | Program Manual | 2018-12-10 | 2018-12-18 | 8 | 0 | 0 | 2 |
| ACRS Presentation Chapter 17 - Quality Assurance and Reliability Assurance, | Program Manual | 2018-12-10 | 2018-12-18 | 8 | 0 | 0 | 2 |
| ACRS Review 2018-12 | Acrs Review | 2018-12-10 | 2018-12-18 | 8 | 0 | 0 | 4 |
| Basis for an RFT Stand COL Item, | Program Manual | 2018-12-18 | 2019-01-21 | 34 | 0 | 0 | 2 |
| Program Manual PM-1218-63882 | Program Manual | 2018-12-19 | 2018-12-21 | 2 | 0 | 0 | 2 |
| Addressing Component Fatigue for NuScale DCA, | Program Manual | 2018-12-19 | 2018-12-19 | 0 | 0 | 0 | 1 |
| Regulatory Audits 2019 | Audit | 2019-01-07 | 2019-12-20 | 347 | 0 | 1 | 5 |
| NuScale Design of Physical Security Systems, | Topical Report | 2019-01-08 | 2019-01-08 | 0 | 0 | 0 | 2 |
| ACRS Review 2019-01 | Acrs Review | 2019-01-18 | 2019-01-31 | 13 | 0 | 0 | 2 |
| EGGS Valve DCA Demonstration Testing, | Program Manual | 2019-01-22 | 2019-01-23 | 1 | 0 | 0 | 2 |
| ACRS Subcommittee Presentation: NuScale FSAR - Emergency Core Cooling System - V | Program Manual | 2019-01-31 | 2019-01-31 | 0 | 0 | 0 | 1 |
| Chapters 2 and 17 ACRS Full Committee, | Program Manual | 2019-02-05 | 2019-02-05 | 0 | 0 | 0 | 2 |
| ACRS Review 2019-02 | Acrs Review | 2019-02-05 | 2019-02-21 | 16 | 0 | 0 | 5 |
| Policy Options for Single Failure Criterion, | Program Manual | 2019-02-06 | 2019-02-06 | 0 | 0 | 0 | 1 |
| Reactor Vessel Flange Tool (RFT) Design Plan and Schedule, | Program Manual | 2019-02-11 | 2019-02-12 | 1 | 0 | 0 | 2 |
| PM-0219-64501, Revision 0 | Program Manual | 2019-02-13 | 2019-03-11 | 26 | 0 | 0 | 4 |
| ACRS Presentation Chapter 11 - Radioactive Waste Management, | Program Manual | 2019-02-13 | 2019-03-11 | 26 | 0 | 0 | 4 |
| ACRS Presentation Chapter 12 - Radiation Protection, | Program Manual | 2019-02-15 | 2019-03-11 | 24 | 0 | 0 | 3 |
| DHRS and ECCS Logic Changes, | Program Manual | 2019-02-19 | 2019-02-19 | 0 | 0 | 0 | 2 |
| ACRS Review 2019-03 | Acrs Review | 2019-03-11 | 2019-03-20 | 9 | 0 | 0 | 5 |
| ACRS Presentation: NuScale Chapter 9, Auxiliary Systems, | Program Manual | 2019-03-14 | 2019-04-02 | 19 | 0 | 0 | 3 |
| Combustible Gas Control, | Topical Report | 2019-03-28 | 2019-03-28 | 0 | 0 | 0 | 1 |
| ACRS Review 2019-04 | Acrs Review | 2019-04-02 | 2019-04-10 | 8 | 0 | 0 | 5 |
| ACRS Presentation: Chapter 4, Reactor Overview, | Program Manual | 2019-04-10 | 2019-04-10 | 0 | 0 | 0 | 2 |
| ACRS Presentation: Chapter 5, Reactor Coolant System and Connecting Systems Over | Program Manual | 2019-04-11 | 2019-04-11 | 0 | 0 | 0 | 2 |
| ACRS Presentation: NuScale Chapters 4 and 5 Full Committee, | Program Manual | 2019-05-01 | 2019-05-01 | 0 | 0 | 0 | 1 |
| ACRS Review 2019-05 | Acrs Review | 2019-05-01 | 2019-05-16 | 15 | 0 | 0 | 5 |
| FSAR Section 3.9.2: Dynamic Testing and Analysis of Systems, Components, and Equ | Program Manual | 2019-05-07 | 2019-05-07 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation: NuScale FSAR Chapter 14, Initial Test Program an | Program Manual | 2019-05-08 | 2019-05-08 | 0 | 0 | 0 | 1 |
| Containment Systems, | Topical Report | 2019-05-09 | 2020-05-20 | 377 | 0 | 0 | 4 |
| ACRS Subcommittee Presentation: NuScale FSAR Chapter 21, Multi-Module Design Con | Program Manual | 2019-05-09 | 2019-05-09 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation: NuScale FSAR Chapter 19, Probabilistic Risk Asse | Program Manual | 2019-05-09 | 2019-05-09 | 0 | 0 | 0 | 1 |
| NuScale Containment Leakage Integrity Assurance, | Topical Report | 2019-05-28 | 2019-05-28 | 0 | 0 | 0 | 1 |
| Mitigation Strategies for Extended Loss of AC Power Event, | Topical Report | 2019-05-31 | 2019-10-29 | 151 | 0 | 0 | 3 |
| Loss of Large Areas Due to Explosions and Fires Assessment, | Topical Report | 2019-06-14 | 2019-06-14 | 0 | 0 | 0 | 1 |
| Mitigation of Beyond-Design-Basis-Events, NuScale FSAR Chapter 20, | Program Manual | 2019-06-14 | 2019-06-14 | 0 | 0 | 0 | 2 |
| ACRS Subcommittee Presentation, NuScale FSAR Chapter 6, Engineered Safety Featur | Program Manual | 2019-06-14 | 2019-06-14 | 0 | 0 | 0 | 1 |
| ACRS Review 2019-06 | Acrs Review | 2019-06-14 | 2019-06-17 | 3 | 0 | 0 | 2 |
| ACRS Subcommittee Presentation, NuScale FSAR Chapter 15, Transient and Accident | Program Manual | 2019-06-17 | 2019-06-17 | 0 | 0 | 0 | 1 |
| NuScale Topical Report: Quality Assurance Program Description for the NuScale Po | Topical Report | 2019-06-24 | 2020-03-06 | 256 | 0 | 0 | 2 |
| TF-3 Modal Demonstration Testing and SIET Tour, | Program Manual | 2019-06-27 | 2019-06-27 | 0 | 0 | 0 | 1 |
| Fluence Calculation Methodology and Results, | Topical Report | 2019-07-02 | 2019-07-02 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation, NuScale FSAR Chapter 20, Mitigation of Beyond-De | Program Manual | 2019-07-03 | 2019-07-03 | 0 | 0 | 0 | 1 |
| ACRS Review 2019-07 | Acrs Review | 2019-07-03 | 2019-07-23 | 20 | 0 | 0 | 5 |
| ACRS NuScale Full Committee Presentation: NuScale FSAR Chapter 3, Design of Stru | Program Manual | 2019-07-09 | 2019-07-09 | 0 | 0 | 0 | 1 |
| ACRS Full Committee Presentation: NuScale Topical Report-Evaluation Methodology | Program Manual | 2019-07-09 | 2019-07-09 | 0 | 0 | 0 | 1 |
| ACRS Full Committee Presentation: NuScale FSAR Chapter 15 - Transient and Accide | Program Manual | 2019-07-09 | 2019-07-09 | 0 | 0 | 0 | 1 |
| ACRS Full Committee Presentation: NuScale Topical Report-Evaluation Methodology | Program Manual | 2019-07-09 | 2019-07-09 | 0 | 0 | 0 | 1 |
| NuScale Applicability of AREVA Method for the Evaluation of Fuel Assembly Struct | Topical Report | 2019-07-23 | 2020-02-27 | 219 | 0 | 0 | 4 |
| NuScale Power Module Short-Term Transient Analysis, | Topical Report | 2019-07-30 | 2019-07-30 | 0 | 0 | 0 | 1 |
| NuFuel-HTP2 Fuel and Control Rod Assembly Designs, | Topical Report | 2019-07-30 | 2019-12-19 | 142 | 0 | 0 | 2 |
| Long-Term Cooling Methodology, | Topical Report | 2019-08-05 | 2020-05-20 | 289 | 0 | 0 | 4 |
| ACRS Review 2019-09 | Acrs Review | 2019-09-09 | 2019-09-09 | 0 | 0 | 0 | 3 |
| ACRS Review 2019-10 | Acrs Review | 2019-10-18 | 2019-10-18 | 0 | 0 | 0 | 5 |
| ACRS Subcommittee Presentation NuScale Topical Report -Accident Source Term Meth | Program Manual | 2019-11-13 | 2019-11-13 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation: NuScale Source Term Methodology Application, | Program Manual | 2019-11-13 | 2019-11-13 | 0 | 0 | 0 | 1 |
| ACRS Review 2019-11 | Acrs Review | 2019-11-13 | 2019-11-26 | 13 | 0 | 0 | 5 |
| ACRS Review 2019-12 | Acrs Review | 2019-12-09 | 2019-12-20 | 11 | 0 | 0 | 5 |
| Regulatory Audits 2020 | Audit | 2020-01-08 | 2020-07-28 | 202 | 0 | 0 | 5 |
| ACRS Review 2020-01 | Acrs Review | 2020-01-08 | 2020-01-08 | 0 | 0 | 0 | 5 |
| ACRS Subcommittee Presentation: NuScale FSAR Chapter 3 - Protection Against Turb | Program Manual | 2020-01-28 | 2020-02-04 | 7 | 0 | 0 | 2 |
| ACRS Subcommittee Presentation: NuScale FSAR - Steam Generator Design, | Program Manual | 2020-01-31 | 2020-01-31 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation: NuScale FSAR Chapter 8 - Electric Power, | Program Manual | 2020-01-31 | 2020-01-31 | 0 | 0 | 0 | 1 |
| ACRS Review 2020-02 | Acrs Review | 2020-02-04 | 2020-02-28 | 24 | 0 | 0 | 5 |
| ACRS Subcommittee Presentation: NuScale Topical Report - Rod Ejection Accident M | Program Manual | 2020-02-17 | 2020-02-17 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation: NuScale Topical Report - Rod Ejection Accident M | Program Manual | 2020-02-17 | 2020-02-17 | 0 | 0 | 0 | 2 |
| ACRS Subcommittee Presentation: NuScale Topical Report- Non-Loss-of-Coolant Acci | Program Manual | 2020-02-17 | 2020-02-17 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation: NuScale Topical Report - Non-Loss-of-Coolant Acc | Program Manual | 2020-02-17 | 2020-02-19 | 2 | 0 | 0 | 2 |
| ACRS Subcommittee Presentation: NuScale Topical Report - Loss-of-Coolant Acciden | Program Manual | 2020-02-17 | 2020-02-17 | 0 | 0 | 0 | 2 |
| ACRS Subcommittee Presentation: NuScale Topical Report - Loss-of-Coolant Acciden | Program Manual | 2020-02-17 | 2020-02-17 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation: NuScale FSAR Topic-Resolution of Chapter 15 Phas | Program Manual | 2020-02-28 | 2020-02-28 | 0 | 0 | 0 | 2 |
| ACRS Subcommittee Presentation: NuScale FSAR Chapter 19 - Probabilistic Risk Ass | Program Manual | 2020-02-28 | 2020-02-28 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation: NuScale FSAR Topic-Resolution of Chapter 15 Phas | Program Manual | 2020-02-28 | 2020-02-28 | 0 | 0 | 0 | 1 |
| ACRS Full Committee Presentation: NuScale - Steam Generator Design, | Program Manual | 2020-02-28 | 2020-02-28 | 0 | 0 | 0 | 2 |
| ACRS Full Committee Presentation: NuScale - Steam Generator Design (Closed Sessi | Program Manual | 2020-02-28 | 2020-02-28 | 0 | 0 | 0 | 1 |
| ACRS Subcommittee Presentation: NuScale Topic - Hydrogen Monitoring, | Program Manual | 2020-03-03 | 2020-03-03 | 0 | 0 | 0 | 1 |
| ACRS Review 2020-03 | Acrs Review | 2020-03-03 | 2020-03-05 | 2 | 0 | 0 | 5 |
| ACRS Full Committee Presentation: NuScale Topical Report-Rod Ejection Accident M | Program Manual | 2020-03-04 | 2020-03-05 | 1 | 0 | 0 | 2 |
| ACRS Full Committee Presentation: NuScale Topical Report-Non-Loss-of-Coolant Acc | Program Manual | 2020-03-04 | 2020-03-04 | 0 | 0 | 0 | 2 |
| ACRS Full Committee Presentation: NuScale Topical Report, Loss-of-Coolant Accide | Program Manual | 2020-03-04 | 2020-03-05 | 1 | 0 | 0 | 2 |
| Public Meeting Presentation: Topic - Emergency Core Cooling System (ECCS) Boron | Program Manual | 2020-03-09 | 2020-03-09 | 0 | 0 | 0 | 2 |
| ACRS Full Committee Presentation NuScale Topic-Probabilistic Risk Assessment wit | Program Manual | 2020-04-03 | 2020-04-03 | 0 | 0 | 0 | 1 |
| ACRS Review 2020-04 | Acrs Review | 2020-04-03 | 2020-04-06 | 3 | 0 | 0 | 2 |
| ACRS Full Committee Presentation: Nuscale Topic - Hydrogen/Oxygen Monitoring | Program Manual | 2020-04-06 | 2020-04-06 | 0 | 0 | 0 | 1 |
| NRC Public Meeting: Revisions to NuScale's EPZ Sizing Methodology Topical Report | Program Manual | 2020-04-08 | 2020-04-08 | 0 | 0 | 0 | 1 |
| Public Meeting Presentation: Topic - Emergency Core Cooling System (ECCS) Boron | Program Manual | 2020-05-11 | 2020-05-11 | 0 | 0 | 0 | 1 |
| Public Meeting Presentation: Topic - Emergency Core Cooling System (ECCS) Boron | Program Manual | 2020-05-12 | 2020-05-12 | 0 | 0 | 0 | 1 |
| ACRS Review 2020-05 | Acrs Review | 2020-05-18 | 2020-05-29 | 11 | 0 | 0 | 3 |
| Topical Report TR-0711-6 | Topical Report | 2020-05-20 | 2020-05-20 | 0 | 0 | 0 | 1 |
| Program Manual PM-0620-70243 | Program Manual | 2020-05-29 | 2020-05-29 | 0 | 0 | 0 | 1 |
| NRC Public Meeting Presentation: Boron Redistribution and Associated Design and | Program Manual | 2020-05-29 | 2020-05-29 | 0 | 0 | 0 | 1 |
| ACRS Full Committee Presentation: NuScale Topic - Boron Redistribution and Assoc | Program Manual | 2020-05-29 | 2020-05-29 | 0 | 0 | 0 | 1 |
| Letter to NuScale Requesting -A for TR-0716-50350 | Topical Report | 2020-06-03 | 2020-06-05 | 2 | 0 | 0 | 3 |
| ACRS Full Committee Presentation: NuScale Topic - Boron Redistribution and Gener | Program Manual | 2020-07-01 | 2020-07-01 | 0 | 0 | 0 | 1 |
| ACRS Review 2020-07 | Acrs Review | 2020-07-01 | 2020-07-30 | 29 | 0 | 0 | 3 |
| Safety Evaluation for , Control Room Staffing Topical report TR-0420-69456 Publi | Topical Report | 2021-02-11 | 2021-02-11 | 0 | 0 | 0 | 1 |
| Building Design and Analysis Methodology for Safety-Related Structures | Topical Report | 2021-06-22 | 2021-06-22 | 0 | 0 | 0 | 1 |
| Applicant Correspondence | Correspondence | 2017-07-25 | 2023-06-29 | 2165 | 0 | 0 | 5 |
| NRC Correspondence | Correspondence | 2017-03-23 | 2024-03-28 | 2562 | 0 | 0 | 5 |
| ACRS Meetings | Meeting | 2018-06-01 | 2020-07-01 | 761 | 0 | 0 | 5 |
| Public Meetings | Meeting | 2017-04-04 | 2024-01-31 | 2493 | 0 | 0 | 5 |
| Other Meetings | Meeting | 2017-03-29 | 2021-11-09 | 1686 | 0 | 0 | 5 |
| All Inspections | Inspection | 2017-07-24 | 2019-07-18 | 724 | 0 | 0 | 5 |